Electric line, permits and errata

Jeano heard from NOVEC recently and the only option they are willing to do is clear a 30 foot swath and run at least some of our electric line above ground. Groan. We had really not wanted to clear so much of the forest. The only good part is that they are responsible for it, not us.

Jeano also met with the county official responsible for granting us our well and septic permits. He didn't see any issues and we should have those within two weeks!

The TJI folks haven't gotten back to us just yet.

We're digging our footers tomorrow! Jean, my mom and Kathy have been on site ALL WEEK putting in long hours getting the measurements right. I wish I could be out there with them:)

Post a comment

(If you haven't left a comment here before, you may need to be approved by the site owner before your comment will appear. Until then, it won't appear on the entry. Thanks for waiting.)

About

This page contains a single entry from the blog posted on September 26, 2003 4:01 PM.

The previous post in this blog was Site Clearing.

The next post in this blog is Digging Footers.

Many more can be found on the main index page or by looking through the archives.

Creative Commons License
This weblog is licensed under a Creative Commons License.